On 13 April 2026 the Supreme Court, bench of Justice Vikram Nath, ordered NHAI, NHIDCL and State Public Works Departments to submit a consolidated report on highway‑encroachment inspections, to form District Highway Safety Task Forces, and to demolish unauthorised structures in the right‑of‑way within 60 days, subject to statutory acquisition requirements. Subsequent interim orders upheld the status‑quo for pending interlocutory applications, directing that demolition may not proceed without compliance with the Control of National Highways (Land and Traffic) Act 2002.
Key Development
Supreme Court, sitting as a bench of Justice Vikram Nath, issued interim directions on 13 April 2026 directing the National Highways Authority of India (NHAI), the National Highways and Infrastructure Development Corporation Limited (NHIDCL) and State Public Works Departments (PWDs) to submit a consolidated report on highway‑encroachment inspections (see p.5 of the order). The Court also mandated the demolition of unauthorised structures in the right‑of‑way (ROW) within 60 days, the formation of District Highway Safety Task Forces within 15 days, and imposed land‑use restrictions of 40 m for residential and 75 m for commercial developments from highway mid‑points (p.5‑6).
Legal Context
The directions are interim and do not resolve individual ownership or Right‑of‑Way disputes. The Court clarified that pending interlocutory applications (IAs) seeking stays on demolition are to be consolidated and heard collectively, with no stay granted to date (p.6‑7). Subsequent orders dated 8 September 2026, 22 September 2026, and 6 October 2026 upheld the status‑quo for several IAs (305732, 305733, 308232), directing NHAI to file responses and extending interim protection (pp.11‑12).
Statutory Framework
The Court emphasized compliance with Section 26 of the Control of National Highways (Land and Traffic) Act 2002, which requires notice, hearing and consideration of representations before any demolition. Accordingly, demolition is prohibited without statutory acquisition and adherence to the Gyan‑Prakash precedent.
Outcome
- NHAI, NHIDCL and State PWDs must submit the required report.
- District Highway Safety Task Forces to be constituted within 15 days.
- Demolition of unauthorised structures ordered, but subject to statutory acquisition; no demolition may occur pending High Court adjudication of individual cases.
- Interlocutory applications remain pending; interim protection continues until High Courts dispose of each matter.
No Dissent
The orders contain no recorded dissenting opinions.
The Court’s interim directions are procedural safety measures and do not constitute a final determination of property rights.
Key findings
- Interim demolition orders are conditional on statutory acquisition and due process.
- All pending interlocutory applications are to be consolidated and heard by the appropriate High Courts.
- District Highway Safety Task Forces must be formed within 15 days.
The outcome
Interim directions issued; demolition ordered subject to statutory acquisition; pending interlocutory applications to be heard collectively; interim protection remains in force.
Statutory references
- Section 26, Control of National Highways (Land and Traffic) Act 2002
Paragraph references
p.5 – report requirement and demolition timeline · p.5‑6 – land‑use restriction distances · p.6‑7 – consolidation of interlocutory applications · pp.11‑12 – status‑quo orders for IAs 305732, 305733, 308232 · para 14‑19 (pp. 12‑16) – clarification on non‑finality of directions · pp. 21‑25 – interim relief details